Adolph Coors Company - Shenandoah Brewery
Elkton, VA
Services
Can Line Addition
Value
$2.5 million
Scope
The project consisted of over
78,000 man-hours of work of which 26,000 man-hours were pipefitter
hours; 34,000 were millwright hours, and the remaining 18,000 were
various other crafts, all employed by R.S. Harritan. Systems installed
included a complete bottle washer system and conveyors, bottle filling
system and conveyors, filling system and conveyors, six- and twelve-pack
case conveyors, pneumatic case conveyor, glass reclamation system, beer
storage tank, SS piping, 100% purge system, sludge beer handling
systems, and a warehouse pallet system.